Project complete - Ipswich
The scope of works for this project included-
-Isolation, draining down and degassing of all services.
-All asbestos containing materials removed ahead of soft strip demolition.
-Removal of 2 No Escalators and associated pit and floor infills.
-Structural openings were formed in the existing concrete floor slabs for the installation of a new customer steel staircase.
-Full strip out and demolition works to Ground, 1st and 2nd floors. -Partial strip out of Mechanical Plant on roof.
-Removal of Latex floor screed throughout.
-Any disturbed fire protection or encasement to existing exposed columns or beams reinstated.
-CCTV Survey to all existing drains.
-New high security separating wall constructed between proposed facias.
-Extensive repairs to existing lifts
-Replacement entrance doors and shopfronts.
-Repairs and decorations to all timber windows.
-Specialist DOFF cleaning to building façade.
-Full decoration of external surfaces.