STRIP OUT | ENABLING WORKS

Former Argos store | Plymouth.

Client | Frasers Group

Location | Plymouth

Value | £280,000

Timing | 5 weeks

 
 

The Main Roof was treated with a new overlay system comprising of new insulation and new Icopal roof finishes, which provides the client with the security of a 10 year insurance backed guarantee. The existing front Facade was cleaned and repaired, including the first and second floor levels above an adjacent ground floor retail unit.

Internally, new apertures were formed within the existing concrete slab which required new structural trimming steels for both the new bespoke Platform lift and customer staircase, the installation of which also formed part of the works. New partitions were erected to form the new stairwell for the clients future fit out contractors and all windows and doors were eased, adjusted and decorated.

Summary of works:

  • New DDA compliant Platform Lift

  • Large Structural openings formed in floor slab

  • Bespoke Steel Staircase Stainless Steel

  • Handrail and glass balustrade

  • New roof overlay system providing 10 year Insurance backed guarantee

  • Lightning Protection replacement

  • Front Fagade

  • Stone cleaning and repairs Floor finish removals

 