ENABLING WORKS | FIT-OUT

Flannels | Southampton.

Client | Frasers Group PLC

Location | Westquay, Southampton

Value | £1,634,000

Timing | 16 weeks

Nature of works

The strip out, enabling works and fit out of the Flannels Store was awarded to us in June 2021 and the works were completed in November 2021, in advance of Christmas trading.

Careful co-ordination and communication with Centre Management created an excellent working relationship and ultimately lead to a successful project, completed within budget and programme. The store was then used by the client as a benchmark for standards moving forward which is testament to the quality of finish we produced.

Works carried out

  • All works carried out within an operational shopping centre

  • Existing H&M shop fit completely removed including M/F ceiling

  • Ceramic floor tiles removed and adhesives ground back to substrate throughout

  • Unit stripped back to shell including all M&E services back to incoming supplies

  • Existing centre management services maintained at all times

  • New Sprinkler System installed

  • Complete new Mechanical and Electrical Services

  • Bespoke Niches and fascias constructed and finished with Durafinish

  • New Doors & Frames to new and existing opens

  • New glass shopfront with Iconic black aerofoil fin detail, unique to Flannels

  • Combination of multiple different floor finishes (tiling, carpets, timber)

  • Various suspended mirrored ceiling features

  • Multiple client appointed trades co-ordinated

 